imageFollowing the process draft release on October 30 and a 30-day public comment period including Advisory Committee and Town staff review, a final process draft of the future Southern Pines Long-Range plan has been completed.

The link below downloads a copy of the entire document, including the main plan chapters as well as the four appendices. Note that Appendix B - the goal, policy and program matrix, is the key, with the rest of the plan referencing and expanding on what the plan policies will work to achieve. To help make the document more accessible via the web, we’ve reduced the file size which in some cases, can make images fuzzier than they’ll appear in final printed copies.

This draft is to be delivered to the Planning Commission for further review and recommendation to Council soon thereafter. Further comments on the plan may be delivered to the Planning Commission in their hearings and review process, or in writing to Town Manager Reagan Parsons by hand, via mail or .

It’s a fairly large file, so give it a little while to download for on-screen viewing, or for saving to your desktop. Printed copies are available for review at the Town library, 170 West Connecticut Avenue, and at the Town’s Planning Department, 180 SW Broad Street.

If you were one of the hundreds of community members that took part in the process, thanks!

Draft Long-Range Plan (7.8 Mb, Acrobat® file)

Friday, October 30, 2009

Long Range Plan: Process Draft

imageAfter months of community input through workshops, questionnaires, interviews, committee review and more, a process draft of the future Southern Pines Long-Range plan has been completed.

The link below downloads a copy of the entire document, including the main plan chapters as well as the four appendices. Appendix B - the goal, policy and program matrix, is the key, with the rest of the plan referencing and expanding on what the plan policies will work to achieve.

This draft is one open for public review through November 30th. A second draft will follow, intending to be delivered to the Planning Commission for further review and recommendation to Council soon thereafter. In short, there’s still time to offer input - simply deliver written comments to Town Manager Reagan Parsons by hand, via mail or .

It’s a fairly large file, so give it a little while to download. Paper copies will be made available beginning Monday, November 2.

Check it out, and if you were one of the hundreds of community members that took part in the process, thanks!

Draft Long-Range Plan (5.7 Mb, Acrobat® file)

Thursday, September 17, 2009

Policy & Programs Workshop: Recap

imageParticipants at the latest Long-Range Plan workshop series held on September 16 were asked to review a draft of the new plan’s policy and program list. Based on what participants wrote and said, the draft goals reflect the Town well - and provide a good outline for important work yet to come.

Due to the length of the entire list of plan goals, policies and programs, consultant Studio Cascade presented worksheets with key policies and 12 different programs relating to them. Participants were given time to review these individually and in groups, along with printed copies of the entire policy list. As with previous workshops, table groups were encouraged to present their findings to the larger audience.

Of those presenting at both workshops - one at the Douglass Center and another at the Recreation Center - programs favored included creating a neighborhood plan for West Southern Pines, updating the recreation and parks plan, allocating additional funds for acquiring and developing parkland, and preparing an urban design plan for the Pennsylvania Avenue corridor to help revitalize and activate the link between West Southern Pines and downtown.

Two written comments that seemed to capture much of the discussion: "Connect east and west Southern Pines via Pennsylvania Avenue to create one town, not east and west" and, "Develop a West Southern Pines neighborhood plan...with the input of neighborhood citizens."

The draft goal, policy and program framework, along with a worksheet sample and a copy of the meeting presentation, are linked below. The entire framework, as refined to reflect input from the day’s workshops, will be included in the draft plan. The draft Southern Pines Long-Range Plan is expected to be ready for public review in October.

Draft policy & program list (340 Kb, Acrobat® file)
Meeting worksheet (172 Kb, Acrobat® file)
Presentation slides (2.0 Mb, Acrobat® file)

Drop-In Center Closing

image Nearly a year since it opened, the Drop-in Center for the Southern Pines Long-Range Plan is closing its doors.

“The center was established as a type of headquarters for the planning process, where folks could come and meet us, ask questions, and tell us what they thought,” said lead consultant Bill Grimes of Studio Cascade. “Now that the plan’s development is nearly complete, it’s time to shift these resources and the dialogue to the Town and its staff.”

According to center staff-person Kathy Hicks, the space saw approximately 30 visitors during a typical four-day schedule - not as many as was hoped, but according to Hicks, most visitors appreciated the chance to spend time with materials, ask questions, and reflect on community issues.

Everything collected during the Drop-in Center’s run, from sign-in sheets, to workshop materials, posters and process results, will be organized and given to the Town’s Planning Department, where it’s expected they’ll be available for review. Questions about materials or other related resources may be directed to consultant Studio Cascade at 509-835-3770, or to Town staff.

The official closing date for the Drop-in Center will be Thursday, September 17. “We really appreciated what the Drop-in Center offered us in terms of having a meeting place and process showcase,” said Grimes, “and working downtown really helped us get to know folks and learn important things about the Town. We hope residents enjoyed having the center as much as we did.”

About

Southern Pines' new long-range plan will engage residents in charting a course for the future. From housing, to transportation, land use to basic services, what should be included? What's working now, and what challenges need addressing? The process will create a comprehensive set of goals and policies to guide decisions 20 years into the future. Follow the process and add your voice!

Read more...


E-mail Links



Drop-In Center

Address: 161 E. New Hampshire Avenue, Downtown
Hours: 1:00 to 6:00 pm, Tuesday, Wednesday, Thursday, Saturday
Phone: 910-692-9807

Advisory Committee